Hampshire and York Streets Utility Upgrade Project
Overview
Critical upgrades to our aging water and sewer infrastructure are planned for:
- Hampshire and York streets between Mariposa and Cesar Chavez streets
- Bryant Street between Precita Avenue and 26th Street
- 23rd and 25th streets between Hampshire Street and Potrero Avenue
- 26th Street between Bryant and Hampshire streets
- Cesar Chavez Street between Hampshire Street and the Bayshore Boulevard on-ramp
This project will include 8-inch and 12-inch ductile iron water main replacement, 16-inch earthquake resistant ductile iron water main installation, sewer replacement, and pavement restoration.
Construction Look Ahead
- Week of July 1st
Excavation and pipeline installation - Bryant Street between Cesar Chavez Street and Precita Avenue
Excavate service transfer pits - York Street between Cesar Chavez and 26th Street
Curb ramp replacement - Intersection of York and 21st streets
- Week of July 8th
Excavate service transfer pits - York Street between Cesar Chavez and 26th Street; York Street between 18th and 20th streets
Service changeovers - York Street between Cesar Chavez and 26th Street
Curb ramp replacement - Intersection of York and 20th streets; Intersection of York and 21st streets
- Week of July 15th
Excavation and pipeline installation - Hampshire Street between 24th and 26th streets
Street base restoration and trenching - York Street between 20th and 21st streets
Curb ramp replacement - Intersection of York and 18th streets; Intersection of York and 20th streets
Check out our What to Expect During Construction fact sheet for a helpful overview.