Stern Grove Emergency Repairs
Overview
SFPUC has released a series of emergency contracts to repair damage done to portions of Stern Grove because of a broken air valve on a nearby large water transmission pipeline in August 2021. This includes removal of debris, restoration of any buildings damaged by mud and water, and stabilization of the hillside.
Stern Grove Restoration Project Update (January 25, 2022)
-
Restoration of damaged buildings is nearly complete.
-
Removal of hazard trees complete.
-
Off hauling of soils and debris from the site continues 7 a.m. to 5 p.m., Monday through Saturday through May on Sloat Blvd.
-
Engineering design is underway for stabilization of the damaged hillside.
-
The SFPUC continues to work closely with Stern Grove Festival and Recreation and Parks Department with the aim to have work completed before the start of the 2022 Summer concert series.