Construction 4-week Look-ahead from June 28, 2024 to July 31, 2024
- Segment 1 - Crags Court - Continue to install concrete street base
- Segment 2 - Berkeley Way from Crags Court to Diamond Heights Blvd. Northern Crossing - Measure and install service changeovers (SF Water Dept.)
- Segment 3 - Gold Mine Drive from Diamond Heights Blvd. to Jade Place - Install pipeline; continue probing for unmarked underground utilities and creating a layout for installing new water pipeline.
The Project has posted two trees for removal: 1 tree at 80 Crags Court and 1 tree at 87 Crags Court.
Reasons for the Trees Removal: The San Francisco Public Utilities Commission (SFPUC) proposes to remove a total of two (2) trees for construction of curb ramps at the above locations within the Gold Mine Drive and Various Side Streets Water Improvements Project WD-2848. The trees will prevent installation of new curb ramps at Crags Court and Berkeley Way to comply with the Americans With Disabilities Act. The SFPUC will pay the In-Lieu Fee to fund planting two City trees.
The Notices and Photos of the trees are posted under the Documents Section on this page. Please direct any questions regarding this action to the SFPUC before the end of the posting period, via the following: San Francisco Public Utilities Commission, ATTN: Stephen Kech, 525 Golden Gate Ave., 12th Floor, San Francisco, CA 94102. Telephone: 415-551-4569. Email: SKech@sfwater.org
Posting Period (30 days) From 06/28/2024 through 07/29/2024.
Please observe all posted "No Parking" signs for the latest details on when, where and at what times the Contractor's work will be proceeding.