Active Alerts

There are no alerts at this time. If you are experiencing a water, power, or sewer emergency or service problem call our 24-hour hotline at 3-1-1 or (415) 701-2311 from outside SF or log on at sf311.org.

Diamond Heights Water Main Replacement

Overview

This project will replace pipes that are approaching the end of their useful life. The project will install 16-, 12-, and 8-Inch ductile iron water mains in two areas:

  1. In the west at Portola Drive from 200 feet west of Clipper Street to 200 feet east of Clipper Street, Clipper Street from Portola Drive to Diamond Heights Boulevard, Diamond Heights Boulevard from Clipper Street to Duncan Street and
  2. In the east on Diamond Street from 27th Street to Diamond Heights Boulevard, 28th and Duncan streets from Douglass to Noe streets, Valley Street from Diamond to Noe streets, and Noe Street from Duncan to Valley streets.

Construction Look Ahead

  • Week of October 2nd
    Pipeline installation - Valley Street from Noe to Diamond Streets
     

  • Week of October 9th
    Pipeline installation - Valley Street from Noe to Diamond Streets
    Service change overs* - 28th Street from Noe to Castro Streets
    Concrete street panel replacement** - Duncan Street from Newburg to Castro Streets
     

  • Week of October 16th
    Pipeline installation - Valley Street from Noe to Diamond Streets
    Service change overs* - 28th Street from Noe to Castro Streets


*Service changeovers may require temporary disruption to household water supply. 24 hours notice will be given.

**Vehicles will be temporarily prohibited from driving over areas where concrete needs to be cured.

 

Check out our What To Expect During Construction fact sheet for a helpful overview.

  • Construction Start: June 2022
  • Construction End: Spring 2024
  • Project Phase: Construction